Concrete Mixing Plant Assembly – Mihail Kogălniceanu

LOCATIONMihail Kogălniceanu, Constanța County
DURATIONmai mult de o lună
EQUIPMENTFaun ATF 500XL 45-3 45 tonnes

Project details

Description:
Kran provided heavy-equipment support for the transport and assembly of a complete concrete batching plant in Mihail Kogălniceanu (Constanța County). The project required multiple cranes and access platforms over several days of coordinated lifting.

Equipment Used:

  • 45t mobile crane
  • 100t mobile crane
  • 21m rubber-wheeled aerial work platform

Location:
Mihail Kogălniceanu, Constanța County

Duration:
July – August 2025

Scope of Work:

  • Lifting and positioning concrete silos
  • Assembly of mixing units and structural frames
  • On-site support with aerial platforms for safe assembly at height

Technical Notes:

  • Truck-mounted cranes with safe lifting capacities up to 100t
  • Deployment included ground stabilization with outriggers
  • Precise rigging and coordinated lifts for tall vertical structures